Over the weekend, President Trump threatened that the United States would not allow American companies to build data centers outside the country, warning that companies that do so could face heavy taxes. In his remarks, he linked domestic opposition to building these facilities with concerns that investments would be diverted abroad and that the U.S. would lose its edge over China. The statement was not accompanied by an official framework. It came just days after the U.S. Department of Commerce announced the first phase of a plan to export packages of American AI technologies to foreign markets.
The gap between the two messages is striking. On one hand, the administration seeks to promote American infrastructure, chips, models, and services worldwide. On the other, the President is signaling that building American infrastructure outside the U.S. could be penalized. At this stage, it is unclear whether the threat will become policy, which companies or projects would be included, and what "building" a data center abroad actually entails: facility ownership, financing, equipment supply, or operating cloud services.
This uncertainty is significant in its own right. AI infrastructure projects require major investments, long-term planning, and commitments from governments, companies, and energy providers. Even without legislation or detailed guidelines, a presidential threat could cause companies and countries to pause decisions until the policy becomes clear.
Export Policy vs. Domestic Politics
Trump’s rationale combines domestic opposition to building data centers in the U.S. with competition against China. Public pushback against data centers is growing in the U.S., driven in part by their impact on electricity bills, energy and water consumption, and competition for land and infrastructure. The President implied that companies might build facilities abroad due to the difficulty of building them domestically.
However, data centers are also built outside the U.S. because cloud and AI services need to be close to their customers, communications networks, and energy sources. Many governments require sensitive infrastructure and data to be operated within their borders as part of their technological sovereignty policies. Therefore, restricting the construction of American data centers abroad will not necessarily bring investment back to the U.S.; it could instead shift it to local providers or companies from other countries.
The national security rationale also requires distinction. If the concern is that Chinese companies will gain remote access to computing power based on American chips, targeted export control rules can address access and usage. Conversely, an exit by American providers from foreign markets could make it easier for Chinese companies to enter them.
Israel’s Exposure
Project Nimbus and the National Supercomputer illustrate two forms of dependency. Under Nimbus, the Israeli government purchases cloud services from Amazon and Google, which have built infrastructure in Israel. The National Supercomputer, established for the Israel Innovation Authority, provides Israeli companies and researchers with computing power based on NVIDIA accelerators through Nebius’s cloud platform.
If an American restriction focuses on ownership and operation, the initial exposure will primarily affect investments and expansions that rely on U.S. cloud providers. If restrictions are later applied to the supply, upgrading, or access to chips, that exposure will expand to facilities operated by non-American entities as well. Having the infrastructure located in Israel supports local processing and service availability, while the ability to expand and upgrade it still depends on suppliers and decisions made outside Israel.
The statement could have an impact even before a policy is formulated. Building a data center requires multi-year commitments from investors, suppliers, and customers, alongside certainty regarding power grid connections. Ambiguity could delay investment decisions, particularly regarding facility expansions and acquiring next-generation accelerators. It could also push partner countries to consider providers that offer greater certainty over the facility's lifecycle. For Israel, the ability to attract international projects will rely on local demand, reliable timelines for power grid connections, and the capacity to offer a secure and stable operating environment.
Three Steps for Israel
First, Israel should open a dialogue with Washington while the policy is still being shaped. If the administration advances restrictions, Israel needs to clarify how they would apply to existing facilities, expansions, and partnerships in which a local entity owns the infrastructure while an American provider helps operate it. Israel could propose an agreed-upon framework for secure projects in partner countries, including terms for customer vetting, access control, and oversight of computing usage. Where necessary, it should also request transitional arrangements and clarifications regarding supply, maintenance, and upgrades for existing projects.
Second, the government should translate compute demand into a phased investment plan. It should begin by mapping which uses require computing infrastructure in Israel, including the processing of sensitive information and essential services, and which could also rely on infrastructure in partner countries. Based on this mapping, the government can set capacity targets and coordinate among the bodies responsible for energy, planning, communications, and procurement. Projects advanced under the plan should be supported by timelines for grid connections, available land, permits, and a plan for operational continuity in an emergency.
Third, reliance on a single provider should be reduced through tenders and contracts that enable migrating data and workloads between providers, alongside backup systems with an additional provider or at a secondary site, depending on service sensitivity. The state should test this capability through periodic failover drills, as the mere existence of a secondary provider does not guarantee a rapid transition. Cooperation with the United States will remain central to this effort, complemented by the diversification of providers and partnerships where practical.
Israel has a foundation on which to offer Washington a partnership in secure advanced computing projects. To turn this partnership into a long-term advantage, it should ensure that companies, researchers, and public bodies have access to sufficient capacity at an affordable cost, and that essential services can continue operating even when access rules change.
Over the weekend, President Trump threatened that the United States would not allow American companies to build data centers outside the country, warning that companies that do so could face heavy taxes. In his remarks, he linked domestic opposition to building these facilities with concerns that investments would be diverted abroad and that the U.S. would lose its edge over China. The statement was not accompanied by an official framework. It came just days after the U.S. Department of Commerce announced the first phase of a plan to export packages of American AI technologies to foreign markets.
The gap between the two messages is striking. On one hand, the administration seeks to promote American infrastructure, chips, models, and services worldwide. On the other, the President is signaling that building American infrastructure outside the U.S. could be penalized. At this stage, it is unclear whether the threat will become policy, which companies or projects would be included, and what "building" a data center abroad actually entails: facility ownership, financing, equipment supply, or operating cloud services.
This uncertainty is significant in its own right. AI infrastructure projects require major investments, long-term planning, and commitments from governments, companies, and energy providers. Even without legislation or detailed guidelines, a presidential threat could cause companies and countries to pause decisions until the policy becomes clear.
Export Policy vs. Domestic Politics
Trump’s rationale combines domestic opposition to building data centers in the U.S. with competition against China. Public pushback against data centers is growing in the U.S., driven in part by their impact on electricity bills, energy and water consumption, and competition for land and infrastructure. The President implied that companies might build facilities abroad due to the difficulty of building them domestically.
However, data centers are also built outside the U.S. because cloud and AI services need to be close to their customers, communications networks, and energy sources. Many governments require sensitive infrastructure and data to be operated within their borders as part of their technological sovereignty policies. Therefore, restricting the construction of American data centers abroad will not necessarily bring investment back to the U.S.; it could instead shift it to local providers or companies from other countries.
The national security rationale also requires distinction. If the concern is that Chinese companies will gain remote access to computing power based on American chips, targeted export control rules can address access and usage. Conversely, an exit by American providers from foreign markets could make it easier for Chinese companies to enter them.
Israel’s Exposure
Project Nimbus and the National Supercomputer illustrate two forms of dependency. Under Nimbus, the Israeli government purchases cloud services from Amazon and Google, which have built infrastructure in Israel. The National Supercomputer, established for the Israel Innovation Authority, provides Israeli companies and researchers with computing power based on NVIDIA accelerators through Nebius’s cloud platform.
If an American restriction focuses on ownership and operation, the initial exposure will primarily affect investments and expansions that rely on U.S. cloud providers. If restrictions are later applied to the supply, upgrading, or access to chips, that exposure will expand to facilities operated by non-American entities as well. Having the infrastructure located in Israel supports local processing and service availability, while the ability to expand and upgrade it still depends on suppliers and decisions made outside Israel.
The statement could have an impact even before a policy is formulated. Building a data center requires multi-year commitments from investors, suppliers, and customers, alongside certainty regarding power grid connections. Ambiguity could delay investment decisions, particularly regarding facility expansions and acquiring next-generation accelerators. It could also push partner countries to consider providers that offer greater certainty over the facility's lifecycle. For Israel, the ability to attract international projects will rely on local demand, reliable timelines for power grid connections, and the capacity to offer a secure and stable operating environment.
Three Steps for Israel
First, Israel should open a dialogue with Washington while the policy is still being shaped. If the administration advances restrictions, Israel needs to clarify how they would apply to existing facilities, expansions, and partnerships in which a local entity owns the infrastructure while an American provider helps operate it. Israel could propose an agreed-upon framework for secure projects in partner countries, including terms for customer vetting, access control, and oversight of computing usage. Where necessary, it should also request transitional arrangements and clarifications regarding supply, maintenance, and upgrades for existing projects.
Second, the government should translate compute demand into a phased investment plan. It should begin by mapping which uses require computing infrastructure in Israel, including the processing of sensitive information and essential services, and which could also rely on infrastructure in partner countries. Based on this mapping, the government can set capacity targets and coordinate among the bodies responsible for energy, planning, communications, and procurement. Projects advanced under the plan should be supported by timelines for grid connections, available land, permits, and a plan for operational continuity in an emergency.
Third, reliance on a single provider should be reduced through tenders and contracts that enable migrating data and workloads between providers, alongside backup systems with an additional provider or at a secondary site, depending on service sensitivity. The state should test this capability through periodic failover drills, as the mere existence of a secondary provider does not guarantee a rapid transition. Cooperation with the United States will remain central to this effort, complemented by the diversification of providers and partnerships where practical.
Israel has a foundation on which to offer Washington a partnership in secure advanced computing projects. To turn this partnership into a long-term advantage, it should ensure that companies, researchers, and public bodies have access to sufficient capacity at an affordable cost, and that essential services can continue operating even when access rules change.